Related Topic: Construction

Russia completes MBIR hydraulic tests

Russia completes MBIR hydraulic tests

Atommash, part of the Volgodonsk branch of AEM Technology, has completed hydraulic tests of the reactor vessel of the MBIR multipurpose sodium-cooled fast neutron research reactor. MBIR is under construction at the site of the Research Institute of Atomic Reactors at Dmitrovgrad, which is in Russia's Ulyanovsk region.

New Nuclear 16 August 2019


Bangladesh completes basemat of second Rooppur turbine hall

Bangladesh completes basemat of second Rooppur turbine hall

The pouring of concrete for the foundation of the turbine building at unit 2 of the Rooppur nuclear power plant under construction in Bangladesh was completed yesterday. The foundation for the turbine hall of Rooppur 1 was completed earlier this year.

New Nuclear 07 August 2019


Atkins contracted for Sizewell C preparatory work

Atkins contracted for Sizewell C preparatory work

UK-based engineering company Atkins, a member of SNC-Lavalin Group, has been awarded a GBP5.0 million (USD6.2 million) contract for the enabling works basic design at the Sizewell C site. It will be the first programme of construction work to start at the proposed twin-EPR nuclear power plant in Suffolk, England.

New Nuclear 25 July 2019


Foundation in place for first Hinkley Point C unit

Foundation in place for first Hinkley Point C unit

Construction of the concrete basemat has been completed for the nuclear island of the first of two EPR units at the Hinkley Point C nuclear power plant in Somerset, England. The major milestone came as the Confederation of British Industry called for the UK government to support the construction of more new reactors.

New Nuclear 28 June 2019


Work starts on Finnish fuel encapsulation plant

Work starts on Finnish fuel encapsulation plant

Finnish waste management company Posiva today announced the start of construction of the used fuel encapsulation plant at the Olkiluoto site in western Finland. Installation of the necessary systems within the underground disposal chambers is also set to begin soon.

Waste & Recycling 25 June 2019


WIPP upgrades makes progress

WIPP upgrades makes progress

Substantial progress is being made in capital improvement projects including the USD288 million Safety Significant Confinement Ventilation System at the Waste Isolation Pilot Plant , the USA's only repository for transuranic wastes, according to the US Department of Energy Office of Environmental Management.
 

Waste & Recycling 24 June 2019


Fuel loading delayed at Finnish EPR

Fuel loading delayed at Finnish EPR

Nuclear fuel will not be loaded into the core of the first-of-a-kind EPR at Olkiluoto until at least the end of August, Finnish utility Teollisuuden Voima Oyj said today. Under the previous schedule, fuel loading had been due to take place this month.

New Nuclear 19 June 2019


Outer dome installed at Karachi 2

Outer dome installed at Karachi 2

The outer safety dome has been installed on the containment building of unit 2 at the Karachi nuclear power plant in Pakistan. The unit is the first of two Chinese-supplied Hualong One reactors being built at the site.

New Nuclear 18 June 2019


Wood awarded Hinkley Point C services contract

Wood awarded Hinkley Point C services contract

Wood plc has been awarded a "multi-million dollar" contract by EDF Energy to provide engineering and technical services to the Hinkley Point C nuclear power plant under construction in Somerset, UK.

Corporate 11 June 2019


BHEL secures Kudankulam contract

BHEL secures Kudankulam contract

Indian company Bharat Heavy Electricals Ltd has secured an INR440 crore (USD64 million) order from Nuclear Power Corporation of India Ltd to erect the turbine generator islands for Kudankulam units 3 and 4.

Corporate 11 June 2019