Installation of containment starts at Chinese SMR

25 October 2021

The steel containment vessel bottom head has been installed for the ACP100 small modular reactor (SMR) demonstration project at the Changjiang nuclear power plant on China's island province of Hainan. China National Nuclear Corporation (CNNC) said the milestone lays a solid foundation for the subsequent construction of the main structure of what it says will be the world's first land-based commercial SMR.

Hoisting of the ACP100 containment vessel bottom head (Image: CNNC)

Construction of the multi-purpose 125 MWe pressurised water reactor (PWR) - also referred to as the Linglong One - officially started on 13 July following final approval for its construction by China's National Development and Reform Commission in early June.

The containment vessel bottom head - which will support the steel containment shell - was assembled on-site from 50 pre-fabricated steel plates. The assembled component was yesterday hoisted into place by crane onto the plant's concrete foundation plate.


The component is put in place on the foundation plate (Image: CNNC)

Once completed, the Changjiang ACP100 reactor will be capable of producing 1 billion kilowatt-hours of electricity annually, enough to meet the needs of 526,000 households, CNNC said. The reactor is designed for electricity production, heating, steam production or seawater desalination.

CNNC announced in July 2019 the launch of a project to construct an ACP100 reactor at Changjiang. The site is already home to two operating CNP600 PWRs, while the construction of the first of two Hualong One units began in March this year. Both those units are due to enter commercial operation by the end of 2026.

Under development since 2010, the ACP100 integrated PWR's preliminary design was completed in 2014. The major components of its primary coolant circuit are installed within the reactor pressure vessel. In 2016, the design became the first SMR to pass a safety review by the International Atomic Energy Agency. The preliminary safety analysis report for a single unit Changjiang demonstration plant was approved in April 2020.

The project at Changjiang involves a joint venture of three main companies: CNNC subsidiary China National Nuclear Power as owner and operator; the Nuclear Power Institute of China (NPIC) as the reactor designer; and China Nuclear Power Engineering Group being responsible for plant construction. Construction time is expected to be 58 months. For the demonstration plant, the reactor vessel is being supplied by Shanghai Boiler Works Limited, the steam generators by a CNNC subsidiary and other reactor internals by Dongfang Electric Corporation.

In October 2015, NPIC signed an agreement with UK-based Lloyd's Register to support the development of a floating nuclear power plant using the ACP100S variant of the CNNC design, a marine version of the ACP100. Following approval as part of the 13th Five-Year Plan for innovative energy technologies, CNNC signed an agreement in July 2016 with China Shipbuilding Industry Corporation to prepare for building its ACP100S demonstration floating nuclear plant.