Sixth Hongyanhe unit achieves first criticality
The Northeast Nuclear and Radiation Safety Supervision Station of the Ministry of Ecology and Environment carried out the first criticality control point inspection of Hongyanhe 6 between 12 and 14 April. At 7.36am local time on 20 April, it released the unit from the critical operation control point, and work began to bring the reactor to first criticality.
China General Nuclear (CGN) said the milestone was reached at 1.13am on 21 April, "marking the official entry of the unit into the operating state with power, and laying a solid foundation for the subsequent ramp-up, grid connection and commercial operation of the unit".
Construction of Phase I (units 1-4) of the plant, comprising four CPR-1000 pressurised water reactors, began in August 2009. Units 1 and 2 have been in commercial operation since June 2013 and May 2014, respectively, while unit 3 entered commercial operation in August 2015 and unit 4 in September 2016.
Phase II of the Hongyanhe plant - units 5 and 6 - comprises two 1080 MWe CGN-designed ACPR-1000 reactors. Construction of unit 5 began in March 2015 and that of unit 6 started in July the same year. Unit 5 achieved first criticality in June last year and entered commercial operation on 31 July. The loading of the fuel into unit 6 began on 25 March this year and was completed on 28 March. The unit will enter commercial operation once it has completed a series of commissioning tests, including a test run lasting 168 hours.
The Hongyanhe plant is owned and operated by Liaoning Hongyanhe Nuclear Power Company, a joint venture between CGN and State Power Investment Corporation, each holding a 45% stake, with the Dalian Municipal Construction Investment Co holding the remaining 10%.
The ACPR-1000 - a three-loop unit with double containment and core-catcher - was launched by CGN in November 2011. In 2012, central planners in Beijing directed China National Nuclear Corporation (CNNC) and CGN, to 'rationalise' their reactor programmes. This meant CNNC's ACP1000 and CGN's ACPR-1000 were 'merged' into one standardised design - the Hualong One (HPR1000).
Yangjiang units 5 and 6 were the first ACPR-1000 units to enter commercial operation, in July 2018 and July 2019, respectively. Units 5 and 6 of the Tianwan plant, also ACPR-1000s, entered commercial operation in September 2020 and June 2021, respectively.