Turbine installation has been completed at the first unit of Turkey's Akkuyu nuclear power plant, paving the way for pre-launch tests and then cold-hot testing of the reactor unit.
Concreting of the outer containment dome of the first unit at Turkey's Akkuyu nuclear power plant took 104 days, with 3511 cubic metres of high-strength self-compacting concrete mix poured.