About WNN
·
Subscribe
Home
·
Energy & Environment
·
New Nuclear
·
Regulation & Safety
·
Nuclear Policies
·
Corporate
·
Uranium & Fuel
·
Waste & Recycling
·
Podcasts & Features
·
Fusion
·
Country Index
About WNN
HOME
/ Operation and maintenance
Canadian regulator issues order on plant restarts
The operators of the Bruce, Darlington and Pickering nuclear power plants must submit data to demonstrate the safe operation of pressure tubes and obtain regulatory authorisation before restarting any currently shut-down reactors at those sites. The Canadian Nuclear Safety Commission says it has issued orders to Bruce Power and Ontario Power Generation out of an "abundance of caution".
Regulation & Safety
·
Wednesday, 28 July 2021
First steam generator removed from Bruce 6
The first steam generator has been removed from Bruce unit 6, marking a significant milestone in the Major Component Replacement project. The unit is the first of six which are to be refurbished as part of a programme to secure the operation of the eight-unit site in Ontario until 2064.
Corporate
·
Tuesday, 27 July 2021
Operator to decide on Taishan 1 outage, says EDF
The decision to take unit 1 of the Taishan nuclear power plant in China's Guangdong province offline to investigate a fuel failure issue lies with the plant operator, EDF said yesterday. However, it said under its own operating procedures for its French units, operation of the EPR would be temporarily halted to carry out such inspections and take corrective measures. It noted the chemical composition of the primary circuit water at Taishan 1 remains within regulatory threshold limits.
Regulation & Safety
·
Friday, 23 July 2021
Tepco anticipates delay in Kashiwazaki-Kariwa restart
The Kashiwazaki-Kariwa nuclear power plant in Japan's Niigata Prefecture will not be restarted until fiscal 2022 (ending March 2023) at the earliest, Tokyo Electric Power Company said in a revised business plan. The company submitted the plan yesterday to the government for approval. Tepco is awaiting regulatory approval to restart units 6 and 7 at the plant.
Corporate
·
Thursday, 22 July 2021
Integrity tests completed at Fuqing 6
Tests have been completed to evaluate the strength and leak tightness of the inner containment of unit 6 at the Fuqing nuclear power plant in China's Fujian province. The unit - the second of two demonstration Hualong One reactors at the site - is scheduled to begin operations by the end of this year.
New Nuclear
·
Wednesday, 21 July 2021
IAEA reviews long-term safety of Bulgarian plant
An International Atomic Energy Agency team of experts has completed a review of the long-term operational safety of units 5 and 6 of the Kozloduy nuclear power plant in Bulgaria. The team assessed the plant's preparedness, organisation and programmes related to long-term operation against IAEA safety standards.
Regulation & Safety
·
Monday, 19 July 2021
Reactor disassembly work completed at Bruce 6
Work has been completed to remove the internal components of the reactor at unit 6 of the Bruce nuclear power plant in Ontario. As part of a 48-month refurbishment project, replacement parts will be installed in the Candu reactor in order to extend the life of the unit by 40 years.
Corporate
·
Thursday, 15 July 2021
Fuel loading under way at Korean APR-1400
Korea Hydro & Nuclear Power has today begun loading fuel assemblies into the core of unit 1 at its Shin Hanul nuclear power plant, days after being granted an operating licence for the reactor. The unit - the first of two APR-1400 reactors at the site - is scheduled to enter commercial operation in March 2022 following tests at various power levels to ensure that all systems operate safely as designed.
New Nuclear
·
Wednesday, 14 July 2021
USA-Ukraine project 'could add a VVER-1000'
Optimisation work at unit 2 of the Zaporozhe nuclear power plant in Ukraine could lead to the addition of 1000 MW of generation capacity if it is also conducted at the country's other reactors, according to the US Department of Energy. The DOE has been working with Argonne National Laboratory and Ukraine's NT-Engineering to help nuclear power plant operator Energoatom enhance its approach to maintenance.
Corporate
·
Wednesday, 7 July 2021
NRC pauses preparation for 40-year licence renewals
The US Nuclear Regulatory Commission has decided to discontinue its considerations of regulatory and other changes to allow reactor operators to apply for 40-year licence renewals - which could conceivably mean 100-year operating lives. It has however recommended, amongst other things, further evaluations to address the potential for reactor operations up to 100 years.
Regulation & Safety
·
Friday, 2 July 2021
Early shutdown for Taiwanese reactor
Taiwan Power Company today announced the permanent closure of unit 1 at its Guosheng nuclear power plant. The 985 MWe boiling water reactor had been scheduled to be decommissioned in late December this year, but a lack of used fuel storage capacity has forced the state-owned company to take the unit offline early in preparation for a major overhaul of the facility.
Corporate
·
Thursday, 1 July 2021
Fifth Hongyanhe unit connected to the grid
Unit 5 of the Hongyanhe nuclear power plant in China's Liaoning province has today been connected to the electricity grid, the China Nuclear Energy Association announced. The 1080 MWe domestically-designed ACPR1000 pressurised water reactor is scheduled to enter commercial operation later this year.
New Nuclear
·
Friday, 25 June 2021
«
43
44
45
46
47
48
»
Keep me informed
Keep me informed