Related Topic: Uprates And Modernisation

First steam generator removed from Bruce 6

First steam generator removed from Bruce 6

The first steam generator has been removed from Bruce unit 6, marking a significant milestone in the Major Component Replacement project. The unit is the first of six which are to be refurbished as part of a programme to secure the operation of the eight-unit site in Ontario until 2064.
 

Corporate 27 July 2021


Reactor disassembly work completed at Bruce 6

Reactor disassembly work completed at Bruce 6

Work has been completed to remove the internal components of the reactor at unit 6 of the Bruce nuclear power plant in Ontario. As part of a 48-month refurbishment project, replacement parts will be installed in the Candu reactor in order to extend the life of the unit by 40 years.

Corporate 15 July 2021


Romania ratifies Cernavoda agreement with USA

Romania ratifies Cernavoda agreement with USA

The Romanian Senate, the upper house of the country's parliament, has ratified an intergovernmental agreement on cooperation to expand and modernise Romania's nuclear power programme that was signed between Romania and the USA in October 2020. Areas for cooperation could include the completion of units 3 and 4 at the Cernavoda nuclear power plant and the refurbishment of unit 1 at the plant.

Nuclear Policies 24 June 2021


Plant upgrades ensure continued TRIGA fuel supply

Plant upgrades ensure continued TRIGA fuel supply

A major renovation project has been completed at TRIGA International's fuel fabrication facility in Romans-sur-Isère, southeastern France. The facility is the only supplier of uranium-zirconium hydride fuel for use in TRIGA-type research reactors. The upgrades will ensure the continued operation of 36 such reactors around the world.

Uranium & Fuel 12 April 2021


Russia makes progress with fast reactor upgrade

Russia makes progress with fast reactor upgrade

Zio-Podolsk has started manufacturing modules for PGN-200M steam generators as part of work to upgrade unit 3 of the Beloyarsk nuclear power plant in the Sverdlovsk district of Russia. Zio-Podolsk is a subsidiary of Rosatom, which said the modernisation work was aimed at extending the operating life of the unit to 60 years.

Corporate 30 March 2021


Bruce Power marks first year of refurbishment project

Bruce Power marks first year of refurbishment project

Bruce Power's Major Component Replacement project remains on track despite a two-month delay caused by the pandemic, the company said yesterday as it marked the first anniversary of the start of work at Bruce 6.

Corporate 24 February 2021


Darlington unit 3 ready for disassembly

Darlington unit 3 ready for disassembly

Darlington unit 3 is ready to begin the next stage of its refurbishment - disassembly - after successful separation of the reactor and its systems from the three remaining operating units at the station. Installation of the final 5-tonne section of steel bulkhead needed for the isolation was completed 10 days ahead of schedule.

Corporate 20 January 2021


Swedish reactors meet new emergency cooling requirements

Swedish reactors meet new emergency cooling requirements

The Swedish Radiation Safety Authority has today approved the independent core cooling systems implemented by the operators of the country's nuclear power plants. The operators were required to introduce such systems following the accident at Fukushima Daiichi. The systems were to be in place by the end of this year in order for the reactors to continue operating.

Regulation & Safety 18 December 2020


Sendai 1 returns to operation with emergency control room

Sendai 1 returns to operation with emergency control room

Kyushu Electric Power Company has restarted unit 1 of its Sendai nuclear power plant in Japan's Kagoshima prefecture having completed construction of a bunkered back-up control centre as required under revised safety regulations. The 890 MWe pressurised water reactor is the first unit to resume operation in the country after building such a facility.

Regulation & Safety 18 November 2020


Local consent clears way for restart of Onagawa 2

Local consent clears way for restart of Onagawa 2

Tohoku Electric Power Company today received approval from Murai Yoshihiro, the governor of Miyagi Prefecture, to restart unit 2 of its Onagawa nuclear plant in the northeastern Japan prefecture. The utility aims to restart the 796 MWe boiling water reactor in fiscal 2022 at the earliest.

Regulation & Safety 11 November 2020