2020 highlighted nuclear's resilience, says World Nuclear Association
The decrease in nuclear output was strongly influenced by the overall fall of around 1% in global electricity demand in 2020 caused by the COVID-19 pandemic, the report says. In addition, nuclear reactors were increasingly being called upon to provide load-following support to the growing share of variable renewable generation.
"In any other year an almost 4% decline in nuclear generation would be an unequivocal disappointment," Bilbao y León says in the preface to the new report. "In 2020 the world's nuclear reactors have shown resilience and flexibility, adapting to changes in demand while ensuring stable and reliable electricity supply."
The capacity factor for the global fleet in 2020 was still high at 80.3%, down from 83.1% in 2019, but maintained the high performance seen over the past 20 years. Nearly two-thirds of reactors had a capacity factor greater than 80% last year.
"There is no age-related trend in nuclear reactor performance," the Association says. "The mean capacity factor for reactors over the last five years shows no significant overall variation with age. With some reactors now being licensed to operate for 80 years, the consistency in performance of reactors regardless of age is notable."
At the end of 2020 there were 441 operable nuclear reactors, with a combined capacity of 392 GWe. This total capacity has remained almost unchanged for the last three years, with new capacity additions being matched by the amount of nuclear capacity being permanently shutdown.
During 2020, five new reactors with a combined capacity of 5521 MWe (net) started up: Barakah 1 in the UAE; Ostrovets 1 in Belarus; Leningrad II-2 in Russia; and, Fuqing 5 and Tianwan 5 in China. However, six reactors with a combined capacity of 5165 MWe (net) were shut down: Fessenheim units 1 and 2 in France; Indian Point 2 and Duane Arnold in the USA; Leningrad 2 in Russia; and, Ringhals 1 in Sweden.
Between 2018 and 2020 there have been 26 reactors permanently shutdown with a total capacity of 20.8 GWe, compared to 20 new reactors starting up, with a total capacity of 21.3 GWe.
"With global electricity demand expected to rebound sharply, there is a real risk that greenhouse gas emissions will do so as well," Bilbao y León said. "More than half of the reactors permanently shutdown in the last few years have done so not because of technical limitations, but because of political phase-out policies or the failure of markets to adequately recognise the value of low-carbon reliable nuclear power. This is a loss of low-carbon generation that the world can ill afford to squander."
However, there are promising signs for nuclear, the Association noted. Already in 2021, four new reactors have been connected to the grid and construction has started on seven reactors, although two reactors have permanently shutdown.
Bilbao y León said: "It is vital that nuclear generation bounces back further and faster, helping displace fossil fuels, thus avoiding a sharp rise in greenhouse gas emissions. The operation of the existing nuclear fleet must be maximised and extended as long as feasible, and the pace and scale of new nuclear construction must increase."
Construction started last year of four new reactors with a combined capacity of 4473 MWe (net). Three of these are in China (San'ao 1, Taipingling 2 and Zhangzhou 2) and one in Turkey (Akkuyu 2).
The median time for construction of reactors grid connected in 2020 was 84 months, down from 117 months in 2019.
The report, which analyses data from the International Atomic Energy Agency's Power Reactor Information Service database, also includes country reports, summarising recent developments in each country with operable reactors and/or reactors under construction.
It also presents four case studies highlighting the contribution nuclear energy makes to greenhouse gas emissions reduction. These case studies include: the Grohnde nuclear power plant in Germany, which has produced 400 TWh of low-carbon electricity; the Haiyang plant in China, which is providing district heating; the Akkuyu plant, the first to be built in Turkey; and Peach Bottom units 2 3 in the USA, which have been approved to operate for 80 years.