Belarusian plant completes hydraulic tests
Wednesday, 4 September 2019
Hydraulic tests of the primary circuit systems and equipment for density and strength have been completed at unit 1 of the nuclear power plant under construction in Belarus. Russia's ASE Group said this phase of pre-commissioning tests at a pressure of 24.5 MPa had been passed easily and in "little more than a day".
The next stage, where the secondary circuit will be tested at a pressure of 11.5 MPa, will be completed within the first 10 days of this month.
ASE completed a test-run of all four of the main circulating pumps of the unit in July.
ASE, the engineering arm of Russian state nuclear corporation Rosatom, is the general designer and main contractor of the project to build Belarus's first nuclear power plant, which is near Ostrovets in the Grodno region. It is being built using Russian VVER-1200 reactors to give 2340 MWe net capacity online. The first unit is scheduled for commissioning this year, with the second unit to be brought online in 2020.
Most Read
Deep Atomic launches SMR for data centres
Friday, 25 October 2024
Framatome to share fast reactor experience with Japan
Friday, 6 December 2024
Czech Republic selects Rolls-Royce SMR for small reactors project
Thursday, 19 September 2024
Study shows existing US sites suitable for new build
Tuesday, 10 September 2024
Podcasts & Features
Podcast: What happened with nuclear energy at COP29?
Podcasts & Features Friday, 29 November 2024
Podcast: What next for UK's record-setting Heysham 2 nuclear power plant?
Podcasts & Features Monday, 11 November 2024
Related Information
Related Links