Financial problems contribute to Bushehr delays
Tuesday, 20 February 2007
Iranian officials deny that payments have been late, and blame the delay on Russia’s refusal to accept payment in euros, instead of US dollars, without contractual amendments. Iran is reported to have settled less than 25% of the January bill and missed the February instalment completely. Speaking in December, Sergei Shmatko of Atomstroyexport, the Russian company building the plant, said the company had already provided a $140 million loan to Iran to finance construction because of late payments.
Russia had agreed to deliver the fresh fuel six months before start up, with first criticality planned for September 2007 and first power in November 2007. Completion of the plant is also being held up by delays of delivery of safety system cooling equipment from "third countries", which now appears to have been delayed until late 2007.
The Bushehr project is excluded from the UN Security Council’s 23 December resolution giving Iran 60 days to suspend uranium enrichment activities.
Further information
WNN: Delaysat Bushehr
Delays in payments by Iran could delay the supply of fuel from Russia for the Bushehr reactor, putting back the start up date. Iranian officials blame the delay on Russia’s refusal to accept payment in euros, instead of US dollars.
Delays in payments by Iran could delay the supply of fuel from Russia for the Bushehr reactor, putting back the start up date. Iranian officials deny that payments have been late, and blame the delay on Russia’s refusal to accept payment in euros, instead of US dollars, without contractual amendments. Iran is reported to have settled less than 25% of the January bill and missed the February instalment completely. Speaking in December, Sergei Shmatko of Atomstroyexport, the Russian company building the plant, said the company had already provided a $140 million loan to Iran to finance construction because of late payments.
Russia had agreed to deliver the fresh fuel six months before start up, with first criticality planned for September 2007 and first power in November 2007. Completion of the plant is also being held up by delays of delivery of safety system cooling equipment from "third countries", which now appears to have been delayed until late 2007.
The Bushehr project is excluded from the UN Security Council’s 23 December resolution giving Iran 60 days to suspend uranium enrichment activities.
Further information
WNN: Delaysat Bushehr
Most Read
_92619.jpg)
Deep Atomic launches SMR for data centres
Friday, 25 October 2024

Czech Republic selects Rolls-Royce SMR for small reactors project
Thursday, 19 September 2024
_84504.jpg)
Framatome to share fast reactor experience with Japan
Friday, 6 December 2024

Iran outlines nuclear energy plans, including first concrete for Bushehr 3 this year
Friday, 27 September 2024
Podcasts & Features
Podcast: World Nuclear Fuel Cycle 2025 (Pt 2)
Podcasts & Features Tuesday, 6 May 2025
