Bangladesh's Rooppur 1 supplies country's first nuclear energy

Rooppur 1, Bangladesh's first nuclear power plant unit, has been connected to the country's grid and supplied its first electricity.
 
(Image: Rosatom)

The trial grid connection took place 15:16 local time, with Nuclear Power Plant Company Bangladesh Limited (NPCBL) describing it as "marking a proud milestone in the history of Bangladesh's nuclear power generation ...  the electricity produced will be supplied to the national grid for about 8-10 hours. During this time, the operational and stability of the integrated management system with turbines, generators, and grids will be closely monitored, and the necessary technical tests will be conducted.

"According to the plan, in the next phase, the power plant will be temporarily disconnected from the national grid for various technical tests. After a break of about 28 hours, it will be reconnected to the grid for about 4-6 hours to complete the necessary technical and operational tests. At each stage of the test, the operational performance of various systems of the power plant, the efficiency of the turbine and generator, and the compatibility with the national grid will be verified. If all technical tests are successfully completed, the commercial operation of electricity supply from the first unit will begin."

Each of the two units at the plant has a capacity of 1,200 MWe. The initial trial grid connection has been with an output of 350 MWe.

Nuclear Power Plant Company Bangladesh Limited said that once there is approval from the Bangladesh Atomic Energy Regulatory Authority for the next phase of trial operations, the power plant will be reconnected to the national grid for trial operation. "In collaboration with Russia, following the completion of a 10-month trial operation, the first unit will begin regular commercial electricity supply at full capacity," it said.

Sama Bilbao y León, World Nuclear Association's Director General, called Rooppur 1 "a transformative investment in the country’s future".

"Its first electricity marks the beginning of decades of reliable, clean power that can fuel economic growth, strengthen energy security and create prosperity opportunities for generations to come. Bangladesh has turned a bold national ambition into reality, and today we are proud to welcome it to the global community of nuclear energy nations. World Nuclear Association and the global nuclear industry stand ready to support Bangladesh as it continues to develop its nuclear energy programme," she said.

Background

In February 2011 Russia's Rosatom signed an agreement for two reactors to be built at Rooppur, about 160 kilometres from the capital Dhaka, for the Bangladesh Atomic Energy Commission. The initial contract for the project, worth USD12.65 billion, was signed in December 2015. The Bangladesh Atomic Regulatory Authority issued the first site licence for the Rooppur plant in June 2016, allowing preliminary site works, including geological surveys, to begin.

Construction of the first of the VVER-1200 reactor units began in November 2017. Construction of the second unit began in July 2018. They have an initial life-cycle of 60 years, with a further 20-year extension possible.

The first batch of nuclear fuel was delivered to the site in October 2023 - that was the moment that the site got its status as a nuclear facility. An operating licence for unit 1 was issued by the Bangladesh Nuclear Regulatory Authority on 16 April this year. The process of loading 163 nuclear fuel assemblies into Bangladesh's first nuclear power plant reactor was completed in May and the unit achieved criticality - a self-sustaining nuclear reaction - at 15:34 on Sunday, 11 October.